Employees were working in an excavation 25 feet deep, 30 feet long. and 6 feet wide dug in type Photo ID: 1449
(Click photo to view original size.)

Category:

Excavations

Hazard:

Cave-In Hazard:

Standard Violated:

29 CFR 1926.652(a)(1) 29 CFR 1926.652(g)(2)

Corrective Action:

Remove employees from the excavation, widen the bottom of the excavation, place the trench shield within 2 feet of the bottom of the excavation, slope the side walls to 1 1/2 : 1, and have the system approved by a Professional Engineer

Description:

Employees were working in an excavation 25 feet deep, 30 feet long. and 6 feet wide dug in type "C" soil. The trench shield was 5-7 feet off the bottom of the excavation resting on steps cut into the sidewall. The system had not been approved by a PE.